HICKORY CREEK SLIP LINING
Cost - $600,000.00
A Water District Project Aimed At Increasing Sewer Capacities For Development within the City of Balch Springs.
Scope - Thurn the old 18" gravity flow sewer outfall main into a pressure pipe and increase
the outflow capability from 2 1/2 million gallons per day to 5 1/2 million gallons per day.
How? By putting a new poly pipe inside the old pipe and connecting to the new pumping
station being constructed on Ravenview Road.
| Then the 4 1/2 mile by-pass line is snaked along the old
main easement.
|
| District employees call it the "Long Black Snake."
|
| Then the old line is dug up and a section removed making a
place to begin the insertion of the new line. You can see the by-pass line in ther background.
|
| And the new line is s - l - o - w - l - y pulled into the old main.
|